Rance tidal power plant

Rance tidal power plant

The Rance tidal power plant ("Usine marémotrice de la Rance" in french, "Stankell vordredan ar Renk" in Breton) is the world's first electrical generating station powered by tidal energy. It is located on the estuary of the Rance River, in Bretagne, France. It is operated by Électricité de France (EDF).

History

An early attempt to build a tidal power plant took place at Aber-Wrac'h in the Finistère in 1925, but due to financial problems, it was abandoned in 1930. The plans for this plant served as the draft for follow-on work. Use of tidal energy is not an entirely new concept; Tidal mills have long existed in areas affected by tides, in particular along the Rance.

The idea of constructing a tidal power plant on the Rance dates to Gerard Boisnoer in 1921. The site was attractive because there is a large average range between low and high tide levels (8 metres, with a maximum equinoctial range of 13.5 metres). The first studies which envisaged a tidal plant on the Rance were done by the Society for the Study of Utilization of the Tides ("Société d'étude pour l'utilisation des marées [SEUM] ") in 1943. Nevertheless, work did not actually commence until 1961. Albert Caquot, the visionary engineer, was instrumental in the construction of the dam, designing an enclosure in order to protect the construction site from the ocean tides and the strong streams.

Construction necessitated draining the area where the plant was to be built, which required construction of two dams; an effort which took two years. Construction of the plant proper commenced 20 July 1963, while the Rance was entirely blocked by the two dams.

Construction took three years and was completed in 1966. Charles de Gaulle, then President of France, inaugurated the plant on 26 November of the same year. Inauguration of the route crossing the plant took place 1 July 1967, and connection of the plant to the French national power grid (EDF)occurred on 4 December 1967.

In total, the plant cost 620 million Francs - roughly 94.5 Million Euros.Fact|date=February 2007

The plant produces 0.012% of the power consumed by France, with a peak rating of 240 Megawatts for its 24 turbines. Annual output is about 600 million kWh, or about 68MW average power.

Description

The barrage is 750 metres long, from Brebis point in the west to Briantais point in the east. It is located south of Dinard and Saint Malo, at the mouth of the river.

The power plant portion of the dam is 332.5 metres long. The tidal basin measures 22.5 km².

Turbines

The plant's turbines utilise the energy of the tides and the river current in turn; and as such are bi-directional.

Assessment

In spite of the high cost of the project, the plant's costs have now been recovered, and electricity production costs are lower than for nuclear power generation. (1.8c per kWh, versus 2.5c per kWh for nuclear)

Environmental Impact

The barrage has caused progressive silting of the Rance ecosystem. Sand-eels and plaice have disappeared, though Sea bass and cuttlefish have returned to the river. By definition, tides still flow in the estuary and the operators, EDF endeavour to adjust their level to minimise the biological impact.

Tourist attraction and a bridge

The tidal power plant is of itself a tourist attraction which attracts 200,000 visitors per year. A canal lock in the west end of the dam permits the passage of 16,000 vessels between the English Channel and the Rance.

Departmental highway 168 crosses the dam and allows vehicles to travel between Dinard and Saint-Malo. There is a drawbridge where the road crosses the lock which may be raised to allow larger vessels to pass.

ee also

*Tidal power
*Tide
*Tide mill

External links

* [http://www.esru.strath.ac.uk/EandE/Web_sites/01-02/RE_info/tidal1.htm University of Strathclyde Rance project case study]
* [http://www.edf.fr/html/en/decouvertes/voyage/usine/retour-usine.html EdF website] in English
* [http://membres.lycos.fr/chezalex/projets/rance/sommaire_rance.htm French language web site on the Rance tidal power plant]
* [http://membres.lycos.fr/larance/ 2nd French language web site on the Rance tidal power plant]
* [http://membres.lycos.fr/usinedelarance/sommaire.html 3rd French language web site on the Rance tidal power plant]

References

Rance tidal power plant article from the French Wikipedia, version on 30 April


Wikimedia Foundation. 2010.

Игры ⚽ Поможем сделать НИР

Look at other dictionaries:

  • Tidal power — Tidal power, sometimes called tidal energy, is a form of hydropower that converts the energy of tides into electricity or other useful forms of power.Although not yet widely used, tidal power has potential for future electricity generation. Tides …   Wikipedia

  • tidal power — Electricity produced by turbines operated by tide flow. Large amounts of power are potentially available from the tides in certain locations, such as Canada s Bay of Fundy, where the tidal range reaches more than 50 ft (15 m), but this potential… …   Universalium

  • tidal power — /taɪdl ˈpaʊə/ (say tuydl powuh) noun the energy which can be harvested from the tides in the ocean through the use of large underwater turbines placed in areas of high tidal movement. Also, tidal energy. Power in the form of electricity can be… …  

  • Rance River — Infobox River | river name = Rance caption = The Rance in Dinan. origin = Bretagne mouth = English Channel coord|48|38|28|N|2|2|26|W|name=English Channel Rance|display=inline,title basin countries = France length = 102 km elevation = discharge =… …   Wikipedia

  • Ocean power in New Zealand — New Zealand has large ocean energy resources but does not yet generate any power from them. TVNZ reported in 2007 that over 20 wave and tidal power projects are currently under development.[1] However, not a lot of public information is available …   Wikipedia

  • VANTROYS — FRANCE (see also List of Individuals) 17.3.1911 Paris/F 24.1.1959 Paris/F Lucien Vantroys started his career in 1932 with the Hydrographic Service of the French Marine once having completed Ecole Polytechnique. In 1936 he was asked by the… …   Hydraulicians in Europe 1800-2000

  • VADOT — FRANCE (see also List of Individuals) 28.3.1914 Beaucourt/F 22.10.1999 Grenoble/F Louis Vadot graduated from the Ecole d Ingénieurs Mécanicien in Nancy and there submitted a PhD thesis on draft tubes as employed downstream of turbines. In 1940 he …   Hydraulicians in Europe 1800-2000

  • Liste des plus grandes centrales au monde — L article suivant énumère cinq des plus grandes stations de puissance dans le monde de chaque type, en termes de puissance électrique installée actuellemnet. Les centrales à énergie non renouvelables sont celles qui fonctionnent en consommant des …   Wikipédia en Français

  • Renewable energy commercialization — The wind, Sun, and biomass are three renewable energy sources …   Wikipedia

  • Pumped-storage hydroelectricity — Hydro storage redirects here. For storage of water for other purposes, see Reservoir. Diagram of the TVA pumped storage facility at Raccoon Mountain Pumped Storage Plant …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”