Overview
Type Inter-city/commuter rail
Status Planning (environmental impact statement phase)
Locale Minnesota and Wisconsin, United States
Termini Minneapolis, Minnesota
Duluth, Minnesota
Operation
Opened 2014 (projected)
Character Surface
Technical
Line length 155 miles (249 km)
Track gauge 4 ft 8 12 in (1,435 mm) (standard gauge)
Operating speed Maximum: 110 mph (177 km/h)
Average: 68 to 78 mph (109 to 126 km/h)[1]
Route map
Unknown BSicon "CONTu"
North Shore Scenic Railroad (summertime heritage railway)
Head station Straight track
Duluth, Minnesota
Junction from left Track turning right
Unknown BSicon "exWBRÜCKE"
Saint Louis Bay
Unknown BSicon "exHST"
Superior, Wisconsin
Unknown BSicon "exHST"
Sandstone, Minnesota (layover facility)
Unknown BSicon "exHST"
Hinckley (proposed Rush Line Corridor)
Unknown BSicon "exAKRZu"
Interstate 35
Unknown BSicon "exHST"
Cambridge
Unknown BSicon "exAKRZu"
U.S. Highway 10
Continuation to left Unknown BSicon "xABZlg"
Empire Builder and Northstar Commuter Rail
Unknown BSicon "eHST"
Coon Rapids - Foley Blvd
Unknown BSicon "AKRZu"
Minnesota State Highway 610
Unknown BSicon "AKRZo"
Interstate 694
Unknown BSicon "ABZgl+xl" Continuation to right
to St. Paul (Empire Builder and proposed Red Rock Corridor)
Bridge over water
Mississippi River
Unused transverse waterway + Unknown BSicon "uENDEr"
Unknown BSicon "xENDEe" + Unknown BSicon "uHACC"
Unknown BSicon "uCONTl"
Minneapolis - Target Field Northstar and Hiawatha Line
Unknown BSicon "exCONTf"
proposed Norwood/Young America corridor

v · d · e

The Northern Lights Express (NLX) is a proposed passenger rail service running 155 miles (249 km) along the corridor between Minneapolis and Duluth primarily in the U.S. state of Minnesota. A portion of the line will run through neighboring Wisconsin to serve Duluth's "Twin Port" of Superior. Plans are to upgrade an existing BNSF Railway freight line to allow trains to travel at up to 110 miles per hour (177 km/h).[2] The train service will provide an alternative to traveling the busy Interstate 35 between Duluth and the Twin Cities or to other destinations along the line such as the casino in Hinckley.

The train will mostly follow the same route as Amtrak's former North Star, except that it will originate in Minneapolis rather than neighboring Saint Paul, and it is planned to stop at a suburban Twin Cities station (probably constructed at Metro Transit's Foley Boulevard bus station). The route follows part of the Northstar commuter rail route which opened in 2009, and will contain the entirety of the proposed Bethel Corridor commuter route, although that service is not expected to be operational by the time NLX opens.

Contents

History

The Northern Lights Express will be the first passenger rail service to Duluth since 1986, when Amtrak discontinued the 50-mile-per-hour (80 km/h) North Star.[2] Alternatives analysis and a corridor assessment report were complete as of summer 2010.[3] The line had initially been projected to open as early as 2012,[4][5][6] though more recent sources have stated 2013 or 2014 as start dates.[7] As of 2010, the project was entering either an 18-month Environmental Impact Statement (EIS) process or a shorter Environmental Assessment (EA) review,[3] but it is unclear which path is being taken. The shorter EA process was strongly advocated by former Rep. James Oberstar, former chairman of the U.S. House Transportation Committee, who represented northern Minnesota.[8]

Discussion about the Northern Lights Express dates back at least a decade. A preliminary feasibility study was conducted around the year 2000, followed by a comprehensive feasibility study in 2006–2007.[4] A joint powers board was established in 2007 consisting of the regional rail authorities for counties along the corridor along with representatives from Minneapolis, Duluth, and the Mille Lacs Band of Ojibwe.[9] The name was given to the line in March 2008 by a vote of the corridor's stakeholders.[10]

A feasibility study was completed in late 2007 which evaluated service at speeds of 79 mph (127 km/h), 110 mph (177 km/h), and 125 mph (201 km/h), and service of 8 round trips per day at 110 mph was recommended. The 79 mph option was discarded because it wouldn't attract enough riders to cover operating costs. NLX supporters hope to receive funds from the Federal Railroad Administration which requires new train projects to show they will operate at a surplus each year, unlike the Federal Transit Administration that funded the Hiawatha and Northstar lines in the Twin Cities.[2] Trains would also operate at a surplus at 125 mph, but higher capital costs and only a modest reduction in travel time made that option look less attractive. The study used the diesel-powered Talgo XXI as a reference, which has poor acceleration above 110 mph[11]

Planning for the line received a big boost at the end of September 2008 when U.S. Transportation Secretary Mary Peters announced that the federal government would contribute $30 million to passenger rail projects across the country. The contribution included $1.1 million for the Northern Lights Express.[12] On September 9, 2011, Transportation Secretary Ray LaHood announced a grant of $5 million to fund environmental and engineering studies for the project.[13]

Required track improvements

The Northern Lights Express is planned to use several segments of BNSF track. Starting from the south, it will run along the Wayzata Subdivision from Target Field to Minneapolis Junction, the Midway Subdivision to Northtown Yard, and then enter the Staples Subdivision—the same as the current Northstar commuter line. However, the NLX will turn north at Coon Creek Junction in Coon Rapids to enter the Hinckley Subdivision, which it will follow to Boylston Junction between Foxboro and Superior, Wisconsin. From Boylston, the train will use BNSF's Lakes Subdivision to reach Superior.

A preliminary study from around the year 2000 projected a cost of $79 million to purchase rolling stock and upgrade track along the existing line, though this apparently only anticipated 79 miles per hour (127 km/h) service.[4] The cost projection grew to $320 million in 2008, and $615 million in 2009, with a "worst case scenario" number of $990 million.[14][15] Up to 80 percent of the cost may be covered by the federal government, only requiring 20% from state and local sources. This is comparable to highway projects which often receive 80% or 90% funding from the federal government,[16][17] and is in contrast to the Hiawatha light rail and Northstar commuter lines which received 50% matching federal funds.

The wide range of cost estimates relates to how much of the 140 mi (230 km) line between Coon Creek Junction and Duluth will need to be upgraded from the current single-track configuration to a double-track corridor. Running double track all the way to Duluth may bring the cost to $990 million, but the NLX organization has preferred to only run double track north to Sandstone. It was also considered key to upgrade the rails to let trains make the trip in two hours or less. At that pace, the trains could do more than one round trip per day, reducing the number of trainsets needed to provide frequent service. However, the NLX organization revisited some slower options in 2010, and is now leaning toward "Option 2" that would mostly run at 90 mph north of the Twin Cities, but would support speeds up to 110 mph between Cambridge and Hinckley. This would significantly reduce the cost and lead to better benefit-cost calculations, but would also reduce the operating margin to barely better than break-even.[1][18] Option 2 will have trains take 2 hours and 17 minutes to make the trip, and drop the average speed from about 78 miles per hour (126 km/h) to about 68 mph (109 km/h). This still compares favorably with the scheduled 3 hours 35 minutes scheduled for the North Star in 1985—a mere 43 mph (69 km/h) average.[19]

As of 2009, the line hosts 12 to 15 freight trains per day.[20] It had at least some Class 4 track[21] which limits freight 50 mph (80 km/h) and passenger traffic to 79 mph (127 km/h), but this would need to be upgraded to Class 5 and Class 6 in order to support 90 mph and 110 mph speeds, respectively.[11] There are more than 150 grade crossings and 12 bridges on this segment which would need to be improved (or eliminated, in the case of some grade crossings). The line has automatic block signaling, but needs centralized traffic control and positive train control installed to support speeds above 79 mph.[22] There are also several sidings along the route which only have manual switches and will need to be automated.[11]

The double-track main line south of Coon Creek Junction is the busiest rail corridor in the Twin Cities metropolitan area. In July 2009, before the Northstar commuter line began operation, this segment hosted 63 trains per day.[20] There are already plans for BNSF to construct a third main line in the area from the junction south to East Interstate (the bridge over Interstate 694). BNSF would then allow allow 22 more passenger trains per day for Northstar, NLX, Amtrak, and possibly other services.[23] The Northstar's Fridley station was built with the future third main in mind, and was initially built as an island platform with track only on the east side, requiring the Northstar train to be on that track when traveling inbound to or outbound from Minneapolis.

References

  1. ^ a b TEMS, Inc.. "Corridor Speed Options: 110-mph vs. 90-mph Evaluation". Northern Lights Express. http://www.northernlightsexpress.org/joomla/images/documents/Fast%20color%20scan%20to%20a%20PDF%20file_10.PDF. 
  2. ^ a b c Bodley, Peter (January 22, 2008). "Passenger rail service gets green light from consultant". ABC Newspapers. http://abcnewspapers.com/index.php?id=1546&task=view&option=com_content. 
  3. ^ a b SRF Consulting Group, Inc. (July 2010). "NLX Open House Boards". Northern Lights Express. http://www.northernlightsexpress.org/joomla/images/stories/NLX/nlx%20open%20house%20boards%20july%202010_web.pdf. Retrieved September 22, 2010. 
  4. ^ a b c Kelleher, Bob (December 12, 2006). "Duluth ponders commuter rail". Minnesota Public Radio. http://minnesota.publicradio.org/display/web/2006/12/11/duluthrail/. 
  5. ^ Kelleher, Bob (February 22, 2008). "Another push for Duluth to Minneapolis rail service". Minnesota Public Radio. http://minnesota.publicradio.org/display/web/2008/02/22/duluthrail/. 
  6. ^ "Proposed Passenger Train 'On Track'". KDLH News 3. February 20, 2008. http://www.northlandsnewscenter.com/news/local/15826647.html. 
  7. ^ "Transportation Interchange". Hennepin County. November 2009. http://hennepin.us/files/HennepinUS/Commissioners/Peter%20McLaughlin,%20District%204/Transportation_Interchange_Nov2009.pdf. Retrieved September 22, 2010. 
  8. ^ "Meeting Minutes". Minnesota Department of Transportation. April 6, 2009. http://www.dot.state.mn.us/planning/passengerrailforum/pdf/MeetingMinutes20090406.pdf. Retrieved December 21, 2009. 
  9. ^ "History of the NLX". Northern Lights Express. http://www.northernlightsexpress.org/joomla/index.php?option=com_content&view=article&id=9&Itemid=7. Retrieved December 14, 2009. 
  10. ^ "Proposed Minneapolis-Duluth Rail Line Given Name". WCCO.com. March 14, 2008. http://wcco.com/local/northern.lights.express.2.677436.html. 
  11. ^ a b c Minneapolis-Duluth/Superior: Restoration of Intercity Passenger Rail Service Comprehensive Feasibility Study and Business Plan (ch. 1–2, ch 3, ch 4–10, appendices). Transportation Economics & Management Systems, Inc., December 2007. Accessed December 18, 2009.
  12. ^ "Duluth-Twin Cities Rail Line On Federal Money List". wcco.com. September 30, 2008. http://wcco.com/local/rail.line.duluth.2.829597.html. 
  13. ^ "Minnesota’s Northern Lights high speed rail project receives $5m grant". Rail.co. September 9, 2011. Archived from the original on September 11, 2011. http://www.webcitation.org/61dFk68JV. Retrieved September 12, 2011. 
  14. ^ Levy, Paul (November 29, 2009). "Mpls.-to-Duluth rail price tag climbs to $1 billion". StarTribune. http://www.startribune.com/local/north/78106422.html. Retrieved December 15, 2009. 
  15. ^ Levy, Paul (December 13, 2009). "MnDOT getting a line on Twin Cities-Duluth rail". StarTribune. http://www.startribune.com/local/north/79181782.html. Retrieved December 15, 2009. 
  16. ^ "Value Engineering in the Federal-Aid Highway Program". Federal Highway Administration. March 28, 2007. http://www.oig.dot.gov/StreamFile?file=/data/pdfdocs/mh2007040.pdf. Retrieved December 21, 2009. [dead link]
  17. ^ "Interstate FAQ". Federal Highway Administration. http://www.fhwa.dot.gov/interstate/faq.htm#question7. Retrieved December 21, 2009. 
  18. ^ Mike Gainor (May 4, 2010). "NLX board studies train speed choices". http://isanti-chisagocountystar.com/detail/57544.html. Retrieved 2010-05-21. 
  19. ^ "National Train Timetables, Effective April 28, 1985 through October 26, 1985". 1985. http://www.timetables.org/browse/?group=19850428&st=0001. Retrieved September 23, 2010. 
  20. ^ a b Minneapolis-St. Paul Metro Area 2009 Railroad Volume and Speed Map. Minnesota Department of Transportation, July 2009
  21. ^ Cambridge Systematics, Inc. (July 31, 2009). "Minnesota Comprehensive Statewide Freight and Passenger Rail Plan: Freight Rail Supply and Demand (Draft Technical Memorandum 2)". Minnesota Department of Transportation. http://www.dot.state.mn.us/planning/railplan/files/DraftTechMemo2.pdf. Retrieved September 21, 2010. 
  22. ^ "Minnesota Comprehensive Statewide Freight and Passenger Rail Plan: Freight and Passenger Rail System Planning (Draft Technical Memorandum 4)". Cambridge Systematics. August 2009. http://www.dot.state.mn.us/planning/railplan/files/DraftTechMemo4.pdf. Retrieved January 6, 2010. 
  23. ^ BNSF Easement Rights and Passenger Rail Capacity Improvements. Minnesota Department of Transportation, September 15, 2009

External links


Wikimedia Foundation. 2010.

Игры ⚽ Нужен реферат?

Look at other dictionaries:

  • Northern Star Council — is a Boy Scout Council headquartered in Saint Paul, Minnesota. The council was formally the Viking Council and Indianhead Council until the two councils merged on July 1, 2005.[1] The council serves communities across central Minnesota and… …   Wikipedia

  • Northern New Jersey Council — Owner …   Wikipedia

  • Northern Light (sonde spatiale) — Pour les articles homonymes, voir Northern Lights. Northern Light …   Wikipédia en Français

  • Northern Counties Committee — The Northern Counties Committee (NCC) was a railway that served the north east of Ireland. It was built to Irish gauge (1,600 mm (5 ft 3 in)) but later acquired a number of 914 mm (3 ft)  narrow gauge… …   Wikipedia

  • northern Mexican Indian — ▪ people Introduction  member of any of the aboriginal peoples inhabiting northern Mexico.       The generally accepted ethnographic definition of northern Mexico includes that portion of the country roughly north of a convex line extending from… …   Universalium

  • National Express East Coast — This article discusses a defunct train operator. For its successor, see East Coast (train operating company). NEEC redirects here. For NEEC Conference, see North of England Education Conference. National Express East Coast …   Wikipedia

  • Holiday Inn Express Hotel & Suites Prince Albert — (Prince Albert,Канада) Категория отеля: 2 звездочный отель Адрес …   Каталог отелей

  • Holiday Inn Express Golden-Kicking Horse — (Голден,Канада) Категория отеля: 3 звездочный отель Адрес …   Каталог отелей

  • Western Express Highway — The Western Express Highway is a north south arterial road in Mumbai, India, stretching from the suburb of Bandra to Dahisar. The convert|25.33|km|mi|2|abbr=on [ [http://www.mcgm.gov.in/contents/subm64ssmno121ver2eng.pdf MCGM] ] highway begins… …   Wikipedia

  • Passenger rail projects in Minnesota — There are several passenger rail projects being discussed in Minnesota. There is currently one existing commuter rail service in the state, the Northstar Line, and one existing long distance intercity rail service, the Empire Builder. Future… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”