Linear scheduling method

Linear scheduling method

Linear Scheduling Method (LSM) is a graphical scheduling method focusing on continuous resource utilization in repetitive activities. It is believed that it originally adopted the idea of Line-Of-Balance method.

LSM is used mainly in construction industry to schedule resources in repetitive activities commonly found in highway, pipeline, high-rise building projects. These projects are called repetitive projects or linear projects. The main advantages of LSM over Critical Path Method (CPM) is its underlying idea of keeping resource work continuously. In other words, it schedules activities in such a way that:

# resource utilization is maximized.
# interruption in on-going process is minimized, including hiring-and-filing.
# effect of learning curve phenomenon is minimized.

These benefits are achieved in LSM by schedule activity start date at the date which will provide such a continuous work flow for the resource. In contrast to CPM, this date scheduled by LSM is not the earliest possible start date of an activity. ...?

Graphical presentation of LSM is also another advantage over Critical Path Method when project consists of repetitive activities.

ee also

*List of project management topics
*Project

*Project management

*Project planning
*Work breakdown structure
*List of project management software

Further reading

* Robert B. Harris and Photios G. Ioannou [http://www.cem.umich.edu/Ioannou/Pubs/CEE98_RSM/PGI_CEE98_RSM.pdf Repetitive Scheduling Method]
* David W. Johnston [http://cedb.asce.org/cgi/WWWdisplay.cgi?5016289 Linear Scheduling Method for Highway Construction]

Linear (or Repetitive,or Time-Location based) Scheduling Software

* [http://www.pcfltd.co.uk/exechome.html QEI Exec]

* [http://www.astadev.com/software/tilos/index.asp Tilos]

* [http://www.vicosoftware.com/Products/Control/tabid/46260/Default.aspx Vico Control 2008]


Wikimedia Foundation. 2010.

Игры ⚽ Нужно сделать НИР?

Look at other dictionaries:

  • Linear programming — (LP, or linear optimization) is a mathematical method for determining a way to achieve the best outcome (such as maximum profit or lowest cost) in a given mathematical model for some list of requirements represented as linear relationships.… …   Wikipedia

  • linear programming — Math. any of several methods for finding where a given linear function of several nonnegative variables assumes an extreme value and for determining the extreme value, the variable usually being subjected to constraints in the form of linear… …   Universalium

  • Critical path method — PERT chart for a project with five milestones (10 through 50) and six activities (A through F). The project has two critical paths: activities B and C, or A, D, and F – giving a minimum project time of 7 months with fast tracking. Activity E is… …   Wikipedia

  • Crew scheduling — is the process of assigning crews to operate transportation systems, such as rail lines or aircraft. Contents 1 Complex 2 4 Parts 3 Real Time 4 Disruptions …   Wikipedia

  • Transposition driven scheduling — (TDS) is a load balancing algorithm for parallel computing. It was developed at the Vrije Universiteit in Amsterdam, The Netherlands as an algorithm to solve puzzles. The algorithm provides near linear speedup with some problems and scales… …   Wikipedia

  • Sequence step algorithm — The Sequence Step Algorithm (SQS AL) is an algorithm implemented in discrete event simulation system to maximize resource utlization. It uses sequence step which is a drawing concept in activity on node network to orderly determine repetitive… …   Wikipedia

  • Virtual Design and Construction — (VDC) is the use of integrated multi disciplinary performance models of design construction projects, including the Product (i.e., facilities), Work Processes and Organization of the design construction operation team in order to support explicit …   Wikipedia

  • Web crawler — For the search engine of the same name, see WebCrawler. For the fictional robots called Skutters, see Red Dwarf characters#The Skutters. Not to be confused with offline reader. A Web crawler is a computer program that browses the World Wide Web… …   Wikipedia

  • Smart grid — Public infrastructure …   Wikipedia

  • DynaRoad — Operating system Microsoft Windows Type Project management software License Proprietary Website www.dynaroad.com …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”