Cologne-Frankfurt high-speed rail line

Cologne-Frankfurt high-speed rail line

The Cologne-Frankfurt high-speed rail line (in German: "Neubaustrecke Köln-Rhein/Main") is a convert|177|km|sing=on long railway line in Germany, connecting the cities of Cologne and Frankfurt. Its route follows the Bundesautobahn 3 for the greater part. The line's grades of up to four percent require trains with a high power-to-weight ratio which is currently only met by third-generation InterCityExpress trains. It was constructed between 1995 and 2002 at a total cost of 6 billion according to Deutsche Bahn.

Operational use

The line starts in Cologne at the "Abzweig Köln-Steinstraße" in the Cologne borough of Porz. Whilst the connection loop to Cologne-Bonn Airport, the Cologne Airport loop, is technically not a part of the high-speed line, it was built as a part of the general refurbishments in the Cologne area due to the line, and hence is generally regarded as part of the project. The line has four stations, Siegburg/Bonn, Montabaur, Limburg Süd and Frankfurt Airport.The line is equipped for speeds up to 300 km/h between Siegburg and Frankfurt, closely following the A3 autobahn.

History

The former Deutsche Bundesbahn (DB) began planning for a network of high-speed lines for both passenger and freight trains in the 1960s. The 1973 federal transport plan included a high-speed line between Cologne and Groß-Gerau (near Frankfurt), as well as between Hanover and Würzburg and between Mannheim and Stuttgart. This plan envisaged that mixed traffic would require:
*maximum grade of 1.25% (occasionally 2.0%)
*curves with small superelevation and minimum radii of 4,800 m to 7,000 m
*maximum line speed of 250 to 300 km/h These specifications would be difficult to achieve either near the traditional Rhine valley route, which follows an entrenched meander, or along DB's preferred route next to the A3, which has long and steep climbs and descents. The second federal transport plan in 1985 (which was drawn up when the first TGV line had been operating for four years) included a passenger train-only railway, which meant that much steeper grades would be acceptable. The technical standards adopted were:
*maximum grade : 4.0%
*minimum radius : 3,350 m
*maximum speed : 300 km/h (186 mph)

DB negotiated with the states of North Rhine-Westphalia, Rhineland-Palatinate and Hesse over the route. Each state had objections to the bypassing of the cities on the Rhine, particularly Bonn, Andernach, Koblenz, Mainz and Wiesbaden and four other routes were examined that passed through some of these. No agreement was reached and the Federal Cabinet agreed on 20 December 1989 to a recommendation of the Transport Minister to adopt the A3 route and, among other things, to include a station at Limburg.cite journal
last =Gough
first =John
title =Neybaustrecke Köln–Rhein/Main
journal =Modern Railways
volume =60
issue =653
pages =33–47
publisher =Ian Allen
month =February | year =2003
accessdate =2007-06-08
]

DB then consulted with the states and community groups over the details of the route. In North Rhine-Westphalia there was considerable debate over the location of the station to serve the Bonn area and on how to serve the Cologne-Bonn Airport. DB decided that the station would be built at Siegburg and that a separate, double line would connect Cologne and the high-speed line to the south with Cologne-Bonn airport for the S-Bahn and ICE traffic. In Rhineland-Palatinate, DB decided that a station would be built north of Montabaur only 21 km north of Limburg Sud, partly to serve Koblenz via the A48, and to reroute a local railway through it.

In Hesse, DB decided to build the Limburg station south of the town at its current location on cost grounds, even though this prevented a connection to the Lahn valley line, which would have provided a connection to Koblenz and Gießen. Options for connections to Wiesbaden were examined in detail, including routing the line through its eastern outskirts. DB eventually agreed to a double-line spur to Wiesbaden along the A66. Options for connections to Frankfurt Airport, the line to Frankfurt central station and to the Riedbahn (the line to Mannheim). It was decided that routing the line into the existing Frankfurt Airport station (now known as the regional station) with two 400 m-long tracks and a 200 m-long track would not be adequate, even if expanded to four or five tracks. DB decided that a separate station across the A3 from the old station would be required and that the line would go on to connect to the Riedbahn both northbound (towards Frankfurt) and southbound (towards Mannheim). DB dropped a proposal for a connection at Westerburg to the Wiesbaden-Frankfurt railway to allow some trains to avoid the airport station to go directly to Frankfurt central station.Walter Engels, Wilfried Zieße: "Die Neubaustrecke Köln–Rhein/Main − eine Zwischenbilanz", in Die Bundesbahn 10/1991, S. pp965–975 de icon]

Planning

Although the route as set out above was adopted under the federal railway development law on 15 November 1993, the last legal challenge to the project was not resolved until September 1998. ["Ein Jahrzehnt für 58 Minuten" in "Frankfurter Allgemeine Zeitung" of 12 July 2001 de icon] In the meantime DB decided to reduce the minimum radius of curves to 3,320 meters and increased the maximum super-elevation of the track to 180 mm (to follow the A3 more closely), reduced the spacing between tracks from 4.70 to 4.50 m (to save space) and increased the area of tunnel cross-sections from 82 to 92 m² (to allow higher speeds for converging trains). The route as finally designed was intended to allow trains to cover the distance between Cologne and Frankfurt in 58 minutes, ["Letzte Gleise der neuen ICE-Strecke verlegt" in "Frankfurter Allgemeine Zeitung" of 11 July 2001 de icon] although the current fastest time is 70 minutes, due to uncompleted work at rail junctions in Cologne and Frankfurt. [Based on winter timetable 2006/2007]

Construction

The construction of the route began on 13 December 1995 with the turning of the first sod at the Frankfurter Kreuz autobahn junction and the last dispute over the route was settled in May 1997. On 13 May Federal Minister of Transport Matthias Wissmann in Siegburg turned the first sod in North Rhine-Westphalia. [cite journal
title =Realisierung der Neubaustrecke kommt voran
journal =Eisenbahntechnische Rundschau
issue =46
pages =313
publisher =
month =June | year =1997
accessdate =
de icon
] The last section to commence construction was the Schloss-Röttgen tunnel on the Cologne-Bonn airport loop, which was required in the settlement of a law case: work on it commenced in December 2000. The first section completed was the new Frankfurt airport station, which went into operation on 30 May 1999.

The opening of the whole route, which had originally been planned for 1999, took place after numerous court challenges and geological problems, at the end of July 2002.cite news
title =Ein Jahrzehnt für 58 Minuten
language =German
publisher =Frankfurter Allgemeine Zeitung
date =12 July 2001
accessdate =
] The last tracks of the route in the Schulwald tunnel were installed on 10 July 2001. In the same month the first trips with diesel locomotives were run to adjust the height of the overhead electric lines on the southern section. On 22 October 2001 for the first time an ICE 3 ran on the line, on a 37 km long section between Frankfurt airport and Idstein. [cite news
title =ICE startet zur Jungfernfahrt Richtung Köln
language =German
publisher =Frankfurter Allgemeine Zeitung
date =23 October 2001
accessdate =
]

During construction, traffic on the neighbouring A3 was significantly affected and up to 48 building sites with a reduced maximum speed of 100 km/h were operating simultaneously on the autobahn. Up to 15,000 people were employed on the construction of the railway line. 7.5 million m³ of earth was removed during the tunnel construction and approximately three million m³ concrete were poured. 1,400 miners were hired and 13 people died in accidents in the building of the tunnels.

Opening and start-up

The symbolic opening of the line took place on 25 July 2002 with a special train carrying approximately 700 honoured guests. On 1 August 2002, the first passenger services commenced, originally with a two-hourly service and later with an hourly service. In December 2002, the full service commenced, integration into the European timetable, although there were many disruptions to services in the first few months due to technical failures.

On 13 June 2004 the Cologne-Bonn Airport loop was put into service. At the end of September 2004 the Siegburg/Bonn station was finally completed.

Route

In Cologne ICE trains follow three paths to reach the high-speed line:
*from the north (Düsseldorf or Wuppertal), running via the low-level of Cologne Messe/Deutz railway station (tracks 11 and 12) − this route is not currently operating due to construction work
*from the west (Aachen) through Cologne main station and over the Hohenzollernbrücke or from the north to the main station and then reversing to re-cross the Hohenzollernbrücke
*from the north over the Hohenzollernbrücke to the main station and continuing around the western bypass of central Cologne and over the Cologne south bridge The first two routes allow trains to run via Cologne-Bonn airport loop line, rejoining the main route at Cologne-Porz-Wahn.

The high-speed line’s dedicated track begins in Cologne-Porz and are located between the Sieg line and the line from Gremberg yard and the Cologne south bridge, which, in effect, becomes the Right Rhine line when it separates at Troisdorf. Between Porz and Troisdorf there are six parallel lines and the speed limit on the HSL is 200 km/h. At Troisdorf the HSL runs through a 627 m tunnel under connecting lines that allow passenger trains running on the Sieg line to transfer to the Right Rhine line and freight trains on the freight lines to transfer to the Sieg line (and vice versa for northbound trains).

In Troisdorf the Right Rhine line leaves the high speed line and runs through Bonn-Beuel towards Koblenz. The HSL follows the Siegstrecke to the rebuilt Siegburg/Bonn station and then turns south to run through the Siegauen-Tunnel under the Sieg and then joins the A3, which it follows closely to Frankfurt Airport. Between the Siegauen-Tunnel and the Main Bridge (near Frankfurt) the speed limit is 300 km/h and from there to the airport station trains run at 160 to 220 km/h.

In the Wiesbaden suburb of Breckenheim a double line connects to Wiesbaden, partly next to the A66 and then next to the Ländchesbahn. Trains run into the Wiesbaden terminal station and can then reverse reverse to go to Mainz and Mannheim. The 13.2 kilometers-long Wiesbaden branch has a maximum speed of about 160 km/h.

Construction on the approach to Cologne

Work is being carried out to create separate tracks for the high-speed line through the heavily used Cologne rail junction from its provisional connection to the conventional line at Köln Steinstraße, where trains are limited to 130-km/h through the points. The line is being extended to Cologne-Mülheim station through Cologne Messe/Deutz railway station (low level). This work was intended to be part of the original high-speed line project, but was dropped to reduce costs. When completed in 2008 this work will reduce the time between Frankfurt/Main and Duesseldorf by 10 minutes. [cite web
last = Siedenbiedel
first =Christian
title =Mehr ICE-Züge nach Köln
publisher =FAZ.net
date =31 August 2006
url =http://www.faz.net/s/Rub8D05117E1AC946F5BB438374CCC294CC/Doc~EF9877139968042E381CD7AF378487908~ATpl~Ecommon~Scontent.html
accessdate = 2007-06-09
]

References


Wikimedia Foundation. 2010.

Игры ⚽ Нужно решить контрольную?

Look at other dictionaries:

  • Cologne–Frankfurt high-speed rail line — Cologne Frankfurt high speed railway Route number: 472 Line number …   Wikipedia

  • Frankfurt-Mannheim high-speed rail line — Frankfurt Mannheim high speed line (the official name is Rhine/Main Rhine/Neckar high speed line) is a proposed high speed railway line from Frankfurt am Main to the Mannheim Stuttgart high speed rail line near Mannheim with speeds of up to 300… …   Wikipedia

  • Hanover-Berlin high-speed rail line — The Hanover Berlin high speed rail line is a 258 kilometre railway line linking the German cities of Hanover and BerlinThe Wolfsburg Berlin section was built as a new line and runs largely parallel to the Lehrterbahn (the old Berlin Hanover… …   Wikipedia

  • Madrid–Barcelona high-speed rail line — [v · d · …   Wikipedia

  • Madrid–Seville high-speed rail line — Technical Line length 471,8 km Track gauge 1435 mm Minimum radius Standard: 4000 m; Absolute: 3250 m Electrification 25 kV, 50 …   Wikipedia

  • Córdoba–Málaga high-speed rail line — Málaga Córdoba high speed rail line marked in blue. Nuevo Acceso Ferroviario a Andalucía …   Wikipedia

  • Madrid–Levante high-speed rail line — Facade of Valencia North Station. The Madrid Levante high speed line connects Madrid with the Mediterranean coast of the Levante Region, specifically with Castile La Mancha, the Valencian Community and the Murcia Region autonomous communities.… …   Wikipedia

  • Madrid–Valladolid high-speed rail line — The Madrid–Valladolid high speed rail line (Spanish language: Línea de Alta Velocidad Madrid Segovia Valladolid) opened for commercial service on 23 December 2007 and is the first instalment of a high speed rail corridor in the north and… …   Wikipedia

  • Madrid-Toledo high-speed rail line — The LAV Madrid Toledo is a Spanish high speed rail line that connects the cities of Madrid and Toledo, a distance of approximately 46 miles. LAV Madrid Toledo Legend …   Wikipedia

  • High-speed rail in Europe — High speed rail is emerging in Europe as an increasingly popular and efficient means of transportation. The first high speed rail lines in Europe, built in the 1980s and 1990s, improved travel times on intra national corridors. Since then,… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”