Lower Churchill Project

Lower Churchill Project

The Lower Churchill Project is a planned hydroelectric project in Labrador, Canada, to develop the remaining 35 per cent of the Churchill River that has not already been developed by the Churchill Falls Generating Station. The Lower Churchill's two installations at Gull Island and Muskrat Falls will have a combined capacity of over 3,074 MW and be able to provide 16.7 Terawatt hours of electricity per year.[1][2]


Contents

Overview

Further development of the Churchill River in central Labrador was planned for after the Churchill Falls Generating Station opened in 1972. However, the government of Québec refused to allow exports of electricity through its territory. The Lower Churchill Project passed an environmental assessment in 1980, but the project was postponed indefinitely due to concerns over market access to Hydro-Québec's electricity transmission system and financing.

According to former Premier Brian Tobin, as Labrador borders Québec, when an agreement was being negotiated to sell the power generated at Churchill Falls, the power either had to be sold to an entity within Québec or it had to pass through Québec. The government of Québec refused to allow power to be transferred through Québec and would only accept a contract in which the power was sold to Québec.[3] Because of this monopsony situation, Hydro-Québec received very favourable terms on the power sale contract. The contract was negotiated to run for a 65-year timespan, running until the year 2041, and according to former Newfoundland Premier Danny Williams, Hydro-Québec reaps profits from the Upper Churchill contract of approximately $1.7 billion per year, while Newfoundland and Labrador receives $63 million a year.[4]

According to long-time Hydro-Québec critic Claude Garcia, former president of Standard Life (Canada) and author of a recent assessment of the utility commissioned by the Montreal Economic Institute, if Hydro-Québec had to pay market prices for the low-cost power it got from the Churchill Falls project in Labrador, the 2007 profit would be an estimated 75 per cent lower.[5]

According to the government of Newfoundland and Labrador, Hydro-Québec has reaped more than $19 billion in profits while Newfoundland has received only $1 billion in revenues from the Churchill Falls project. Québec refused to renegotiate the project, which doesn’t expire until 2041.[6] Due to the coercion involved in that deal, Newfoundland and Labrador has sought an alternate route for the Lower Churchill Project that bypasses Québec.[7]

A $6.2 billion deal between Newfoundland and Labrador’s Nalcor Energy and Halifax-based Emera was announced on November 18, 2010.[8] Nalcor Energy will spend $2.9 billion to build a power generating facility at Muskrat Falls, while Emera will invest $1.2-billion in the Maritime Transmission Link underwater power connection and $600 million in the Muskrat Falls facility in exchange for 20% of the 800-megawatts of capacity.

Construction of the first phase (Muskrat Falls Generating Facility, Labrador-Island Transmission Link and Maritime Transmission Link) is expected to be completed by the end of 2015, while the second phase (Gull Island Generating Facility) will not proceed until electricity demand strengthens.

Benefits

The project is expected to provide a long-term, sustainable, and renewable energy supply that will enable rate stability and energy security for the province, leading to increased economic growth. It will also enable the retirement of the inefficient Holyrood Thermal Generating Station, which will address air quality issues from burning fuel oil for electricity generation.

With the completion of Phase 1, Newfoundland and Labrador will have an electricity system that will be over 98% carbon free. The development of Muskrat Falls will avoid approximately 96 million tonnes of emissions by 2065, a significant number for a small province.[9]

Phase 1

Muskrat Falls Generating Facility

Muskrat Falls
Location Canada
Newfoundland and Labrador
Coordinates 53°14′44.3″N 60°46′22″W / 53.245639°N 60.77278°W / 53.245639; -60.77278Coordinates: 53°14′44.3″N 60°46′22″W / 53.245639°N 60.77278°W / 53.245639; -60.77278
Construction began 2001
Construction cost C$2.9 billion
Owner(s) Newfoundland and Labrador Hydro
Dam and spillways
Impounds Churchill River
Reservoir
Surface area 41 km2
Power station
Turbines 4 x Kaplan turbines
Installed capacity 824 MW

The Muskrat Falls Generating Facility 53°14′44″N 60°46′17″W / 53.24556°N 60.77139°W / 53.24556; -60.77139 (Muskrat Falls Generating Facility) will consist of a generation station with a capacity of 824 MW and a powerhouse which will contain four Kaplan turbines. The concrete dam will be built in two sections (on the north and south abutments of the river): the north dam will be 32 m high and 432 m long and the south dam will be 29 m high and 325 m long. The reservoir will be 59 km long with an area of 101 km2. The area of inundated land will be 41 km2 at full supply level. Two 230kV AC transmission lines will connect with the Labrador-Island Transmission Link.

The Muskrat Falls development of the Lower Churchill Project will begin in 2011 and is expected to take approximately six years.[10]

Labrador-Island Transmission Link

Emera and Nalcor will form a joint venture to construct transmission facilities from Labrador to Newfoundland at a cost of $2.1 billion.

The Labrador-Island Transmission Link will be a 800MW 1,200 KM High-voltage direct current (HVDC) system[11] from Gull Island in central Labrador to an area near Soldiers Pond on the Avalon Peninsula. This work will result in at least one million person hours of engineering and project management employment and 2.5 million person hours of construction employment in the province.

Key components include:

Construction of the Labrador-Island Transmission Link would take four years, followed by a year long commissioning project.

Maritime Transmission Link

Emera will construct and own a $1.2-billion underwater power connection from Newfoundland to Nova Scotia, to be known as the Maritime Transmission Link. This will enable future electricity exports to the Maritime provinces and the United States.

Major components include:

  • Overhead high-voltage AC transmission lines connecting the Newfoundland Island transmission grid to Bottom Brook Converter Station
  • Bottom Brook Converter Station (500 MW) AC to HVDC
  • Overhead HVDC transmission lines from Bottom Brook to Cape Ray
  • Submarine cables across the Cabot Strait to Lingan, Nova Scotia (180 km)
  • Cape Breton Converter Station (500 MW) HVDC to AC, tying into the existing Nova Scotia transmission grid

Transmission Lines

The transmission lines are designed to be:

  • 203 km long for the 735 kilovolt (kV) line between Gull Island and Churchill Falls; and
  • 60 km long for the double-circuit 230 kV line between Muskrat Falls and Gull Island.

Both transmission lines will be supported by lattice-type steel structures and located north of the Churchill River, requiring a cleared right of way approximately 80 m wide in addition to the existing right of way.

Phase 2

Gull Island

The Gull Island facility will consist of a generation station with a capacity of 2,250 MW and the powerhouse will contain five Francis turbines. The dam will be a concrete-faced, rock-fill construction 99 m high and 1,315 m long establishing a 213 km2 reservoir with a full supply level of 125 m above sea level. The reservoir will be 232 km long and the incremental area of inundated land will be 85 km2 at full supply level.

See also

References

  1. ^ "Nalcor Energy Website". http://www.nalcorenergy.com/content.asp?page=317. Retrieved 2009-10-05. 
  2. ^ "Lower Churchill Project Website". http://www.lowerchurchillproject.ca/LCWeb/LowerChurchill.nsf/GeneralDocs/A6496EB6D3B13269A32571FD0066CC71?OpenDocument&menucat=About&submenucat=&linkname=Lower%20Churchill%20Project. Retrieved 2009-10-05. [dead link]
  3. ^ "Speaking notes from an address by Brian Tobin". Premier's Address on Churchill Falls to the Empire Club, Toronto (Government of Newfoundland and Labrador). November 19, 1996. http://www.releases.gov.nl.ca/releases/1996/exec/1119n06.htm. Retrieved June 9, 2010. 
  4. ^ Moore, Lynn (November 30, 2009). "Newfoundland challenges Churchill Falls hydro deal with Quebec". Canwest News Service (Montreal Gazette). http://www.canada.com/Newfoundland+challenges+Churchill+Falls+hydro+deal+with+Quebec/2286897/story.html. Retrieved 2009-12-01. [dead link]
  5. ^ Baril, Hélène (4 February 2009). "Privatisation d'Hydro-Québec: Claude Garcia s'explique" (in French). La Presse (Montreal). http://lapresseaffaires.cyberpresse.ca/economie/energie-et-ressources/200902/04/01-823900-privatisation-dhydro-quebec-claude-garcia-sexplique.php. Retrieved 2009-12-14. 
  6. ^ Bailey, Sue (18 November 2010). "$6.2B deal reached for Lower Churchill power project". The Star (Toronto). http://www.thestar.com/business/article/892746--6-2b-deal-reached-for-lower-churchill-power-project. 
  7. ^ http://www.canada.com/montrealgazette/story.html?id=17f52755-7ede-45a5-8b2f-6a8b7d004957
  8. ^ McCarthy, Shawn (18 November 2010). "Churchill hydro deal signals era of Atlantic co-operation - The Globe and Mail". The Globe and Mail (Toronto). http://www.theglobeandmail.com/globe-investor/atlantic-canada-power-deal-reshapes-market/article1804039/. 
  9. ^ http://www.nalcorenergy.com/assets/lcp%20background%20information%20november%2018%202010.pdf
  10. ^ http://www.nalcorenergy.com/assets/lcp%20background%20information%20november%2018%202010.pdf
  11. ^ http://www2.mpmo-bggp.gc.ca/MPTracker/projectsummary-resumedeprojet.aspx?pid=94

Wikimedia Foundation. 2010.

Игры ⚽ Нужен реферат?

Look at other dictionaries:

  • Churchill Falls Generating Station — Churchill Falls Generating Station …   Wikipedia

  • Churchill River (Atlantic) — Churchill River Origin Smallwood Reservoir, Labrador Mouth Atlantic Ocean Basin countries Canada Length 856 km (532 mi) Source elevati …   Wikipedia

  • Churchill Falls (Labrador) Corporation Limited — Churchill Falls (Labrador) Corporation Type Subsidiary Newfoundland and Labrador Hydro Nalcor Energy (65.8%) Hydro Québec (34.2%) Industry Electricity …   Wikipedia

  • Churchill River — River, central Canada. Rising in southwestern Saskatchewan, it flows east across Saskatchewan and northern Manitoba and turns northeast into Hudson Bay at Churchill. About 1,000 mi (1,609 km) long, it has many rapids and passes through several… …   Universalium

  • Churchill House, Hantsport — Churchill House Established 1966 Location 6 Main Street, Hantsport, Nova Scotia Canada Type Munic …   Wikipedia

  • Churchill tank — Tank, Infantry, Mk IV (A22) Tank, Infantry Mk IV Churchill IV (75mm) Type Infantry tank Place of origin …   Wikipedia

  • Churchill Machine Tool Company — The Churchill Machine Tool Company Limited Type Machine Tool Manufacturer Industry Engineering Fate Taken over, liquidated …   Wikipedia

  • Churchill, Somerset — Coordinates: 51°20′07″N 2°47′47″W / 51.3354°N 2.7963°W / 51.3354; 2.7963 …   Wikipedia

  • Nelson River Hydroelectric Project — Powerplants (existing and planned) of the Nelson River Hydroelectric Project, Manitoba, Canada (2006). The Churchill Diversion diverts part of the Churchill at South Indian Lake south into the Rat River branch of the Burntwood River. The Nelson… …   Wikipedia

  • Manhattan Project — This article is about the atomic bomb project. For other uses, see Manhattan Project (disambiguation). Manhattan District The Manhattan Project created the first nuclear bombs. The Trinity test …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”